BE337
CM337; PROFESSIONAL PRACTICE/ CONTRACT PROCEDURES AND ADMINISTRATION
TEST NO 1;
FEEDBACK (HOW YOU SHOULD HAVE APPROACHED THE QUESTIONS)
QUESTION
ONE
Needs for
having standard conditions for building contract
1. What is the use of form of contract?
……
……
2. What does the form do? For instance
ü Modify the general law i.e. transfer some risk
from contractor to employer regarding damage to the works.
ü Etc.
3. Define other contract documents
4. Etc.
QUESTION
TWO
Necessity
of including clause no 3 in the NCC to specifically give powers to the
Architect to issues instructions.
………………..
1. Briefly elaborate the nature of the contract,
particularly parties’ pt the contract, ‘privity of contract’.
2. Go to explain the necessity
It is
important to plan the flow of your answer
QUESTION THREE
(i)& (ii) were straight forward, just to
give the meaning of the terms, illustration/ and examples would have attached
more credits.
iii. Defenses open to contractor
ü Agreed sum is a penalty
ü Omission of date in contract
ü Waivers
ü Final certificate
ü Employer causing delay
ü Breach of condition precedent
ü Extension of time
ü Etc.
iv. If liquidated damages provision fail;-
Employer may sue the contractor for
unliquidated damages. In this case the employer to prove in court of law that
there was indeed a breach.
More explanations