BE337 CM337;
PROFESSIONAL PRACTICE/ CONTRACT PROCEDURES AND ADMINISTRATION
TEST NO 2; FEEDBACK
(HOW YOU SHOULD HAVE APPROACHED THE QUESTIONS)
QUESTION
ONE
a) Procedure to be followed for completion of the works
1.
The employer to employ and pay other persons to
carry out and complete the works.
2.
The contractor on request by employer/architect
within 14 days to assign sub-contracts for supply materials / carry out works.
3.
Employer to pay suppliers / sub-contractors for
materials / works not already paid for by contractor.
4.
Contractor when required by architect to remove from
site his temporary buildings, plant, etc within 30 days. Failure to do so the
employer may sell and hold net proceeds to contractor’s credit.
5.
Until completion of the works, employer not bound to
make any further payment to the contractor.
6.
Etc.
NOTE; it is
crucial to demonstrate understanding of the procedures to be followed
b) Determination of final payment due to/from
contractor:-
Architect to certify taking into consideration,
issues under (A) and (B) below
(A)
Amount of expenses properly incurred by employer –
elaborate
(B)
Amount which would have been payable on due
completion in accordance the contract Brief explanation.
If the sum of (A) is greater than
(B), the difference is an amount due from contractor to employer; and vice
versa.
QUESTION
TWO
Reasons for extension of time under
clause 26 of NCC form are works delayed beyond date of completion / time
previously fixed under this clause due to:-
a)
Employer’s risks under Cl 22 (1) c
b)
Exceptionally inclement weather
c)
Architect’s instruction under Clauses:- 3 – authority of architect to issue
instructions; 13.1 – variations; 24.2 postponement of works; or 39.2
–antiquities
d)
Contractor’s non receipt of necessary information
applied for in good time,
e)
Delay by artists etc. engaged by employer
f)
Opening up for inspection etc. – Cl 8.3 - where work is in accordance with
contract
g)
Contractor’s inability to obtain materials etc.
essential for the works
h)
Contractor’s compliance with statutory requirements
–Cl 6.1
i)
Employer’s delay to hand over site
j)
Employer’s delay to pay contractor.
Note; demonstrating understanding of the
reasons through explanations was required.
Comparison of Clause 27 with Clause
26:-
Provisions under clause 26 that
entitle the contractor to extension of time that may also be attributed to default on the on the
part of employer and/or architect (with the exception of Clause 27.1 (h) which
has no equivalent in Clause 26), are the ones that give the contractor right to
claim for loss and expense.
No comments:
Post a Comment