Let Us Share News,Stories, Opportunities,Experiences, Resources,Knowledge,wisdom, Inspirations,Success and even Failures.... Let Us Share! Our Present and Future is in our hands.
Sunday, September 22, 2013
Monday, June 24, 2013
POWER POINT PRESENTATIONS
ALL SCEM FINAL YEAR STUDENTS
My apologies for delay in posting these general guidelines for power point presentations, it is my expectation that it going be of help in the course of preparing your final dissertation presentations.
ALL THE BEST!
POWERPOINT
PRESENTATIONS
General Guidelines
By, Suma Mwaitenda 2013
Contents.
Approach
& a Clue
Purpose of
your presentation
General Guideline
Important
information
TIP
End
- Approach and a clue
Approach
the presentation like a HAMBURGER
Try to imagine the layers in the burger...
HAVE AN
INTRODUCTION:
° Here
create awareness
° Set
context of your presentation
BODY: Here is where you have your main points so
present evidence and findings
CONCLUSION;
Make your summary and recommendations
- Purpose of your presentation
What is the PURPOSE of your presentation?
The purpose of my presentation
today is to....... (Summarize your problem topic)
How are you going to do this?
To inform (facts)
To inspire (feelings)
To persuade (opinions)
To motivate (action)
- GENERAL GUIDELINE
Remember the 30 / 20 / 10 rule for PowerPoint
presentations:
Minimum size 30 font
For a 20 minute presentation
Only using 10 slides (you
may need to use more; but remember ‘quality not quantity’)
General Cont…
Always
remember…..
Less is more: only use keywords on
each slide – not long sentences
If using graphs & figures, they
must be labelled; font size not too small
Must have informative legend, title, x and y axes correctly labelled.
Must have informative legend, title, x and y axes correctly labelled.
Be cautious about the overuse of
technical animation in PowerPoint – it can be very distracting.
Make sure that the following information
is included:
Cover page (with name, topic and
date)
Problem Statement (purpose of presentation)
Agenda/Table of Contents (not
critical but gives a good sense of presentation flow for audience)
Research Methods
● Findings
/ Results
Recommendations
● Implementation
Plan (if applicable)
Conclusion
● Thanks
- TIP
If possible, do a DRY RUN before
your final presentation: to ensure your presentation will be professional,
slick and polished (and not a first attempt)!
Know your audience & be
comfortable with them
Present with Passion & Energy
- END
Thank
you!
Saturday, June 22, 2013
FEEDBACK
TEST NO. I
BE337
CM337; PROFESSIONAL PRACTICE/ CONTRACT PROCEDURES AND ADMINISTRATION
TEST NO 1;
FEEDBACK (HOW YOU SHOULD HAVE APPROACHED THE QUESTIONS)
QUESTION
ONE
Needs for
having standard conditions for building contract
1. What is the use of form of contract?
……
……
2. What does the form do? For instance
ü Modify the general law i.e. transfer some risk
from contractor to employer regarding damage to the works.
ü Etc.
3. Define other contract documents
4. Etc.
QUESTION
TWO
Necessity
of including clause no 3 in the NCC to specifically give powers to the
Architect to issues instructions.
………………..
1. Briefly elaborate the nature of the contract,
particularly parties’ pt the contract, ‘privity of contract’.
2. Go to explain the necessity
It is
important to plan the flow of your answer
QUESTION THREE
(i)& (ii) were straight forward, just to
give the meaning of the terms, illustration/ and examples would have attached
more credits.
iii. Defenses open to contractor
ü Agreed sum is a penalty
ü Omission of date in contract
ü Waivers
ü Final certificate
ü Employer causing delay
ü Breach of condition precedent
ü Extension of time
ü Etc.
iv. If liquidated damages provision fail;-
Employer may sue the contractor for
unliquidated damages. In this case the employer to prove in court of law that
there was indeed a breach.
More explanations
FEEDBACK II
TEST NO II
BE337 CM337;
PROFESSIONAL PRACTICE/ CONTRACT PROCEDURES AND ADMINISTRATION
TEST NO 2; FEEDBACK
(HOW YOU SHOULD HAVE APPROACHED THE QUESTIONS)
QUESTION
ONE
a) Procedure to be followed for completion of the works
1.
The employer to employ and pay other persons to
carry out and complete the works.
2.
The contractor on request by employer/architect
within 14 days to assign sub-contracts for supply materials / carry out works.
3.
Employer to pay suppliers / sub-contractors for
materials / works not already paid for by contractor.
4.
Contractor when required by architect to remove from
site his temporary buildings, plant, etc within 30 days. Failure to do so the
employer may sell and hold net proceeds to contractor’s credit.
5.
Until completion of the works, employer not bound to
make any further payment to the contractor.
6.
Etc.
NOTE; it is
crucial to demonstrate understanding of the procedures to be followed
b) Determination of final payment due to/from
contractor:-
Architect to certify taking into consideration,
issues under (A) and (B) below
(A)
Amount of expenses properly incurred by employer –
elaborate
(B)
Amount which would have been payable on due
completion in accordance the contract Brief explanation.
If the sum of (A) is greater than
(B), the difference is an amount due from contractor to employer; and vice
versa.
QUESTION
TWO
Reasons for extension of time under
clause 26 of NCC form are works delayed beyond date of completion / time
previously fixed under this clause due to:-
a)
Employer’s risks under Cl 22 (1) c
b)
Exceptionally inclement weather
c)
Architect’s instruction under Clauses:- 3 – authority of architect to issue
instructions; 13.1 – variations; 24.2 postponement of works; or 39.2
–antiquities
d)
Contractor’s non receipt of necessary information
applied for in good time,
e)
Delay by artists etc. engaged by employer
f)
Opening up for inspection etc. – Cl 8.3 - where work is in accordance with
contract
g)
Contractor’s inability to obtain materials etc.
essential for the works
h)
Contractor’s compliance with statutory requirements
–Cl 6.1
i)
Employer’s delay to hand over site
j)
Employer’s delay to pay contractor.
Note; demonstrating understanding of the
reasons through explanations was required.
Comparison of Clause 27 with Clause
26:-
Provisions under clause 26 that
entitle the contractor to extension of time that may also be attributed to default on the on the
part of employer and/or architect (with the exception of Clause 27.1 (h) which
has no equivalent in Clause 26), are the ones that give the contractor right to
claim for loss and expense.
Subscribe to:
Posts (Atom)